The revitalization project is expected to be complete by July 2026, with work carefully phased to minimize disruption.
- Start of Construction: July 21, 2025
- Estimated Completion: July 2026
- Contractor: Radmacher Brothers Excavation Company
Phase 1 (July - October)
Phase 1 location: South Street, Oak Grove Street, Shawnee Avenue, Pocahontas Street, Stanley Boulevard, Lee Avenue, S Elm Street, and S Old County Road.
Phase 2 (October - February)
Phase 2 location: Cliff Drive
Phase 3 (February - June)
Phase 2 location: Cliff Drive, Chippewa Avenue, Elm Street, South Sunshine Street, Lee Avenue, Cherokee Street, Vaughn Road